120127 NET Response
. The only place for news and information for Wilford residents

Click here for the Wilford Discussion Forum

PC Matt Pooley

07702 141876

 

Nottinghamshire Police

Other Useful Numbers

 

Home
Up

 

Current Flooding Situation

 

Quick Links

Refuse Collection Calendar

Advice Centre

Report Graffiti Online

Buses

NCT Bus Route Maps

Service 1

Service 2

Service 3

Service 4 (Unilink)

Service 48

LocalLink L1

Airport (Red Flyer)

Ruddington Connection

Medilink

Shoplink (Asda/Morrisons)

 

Wilford Property Prices

 

Local Websites

Iremongers Pond

wilford.org

ladybay.co.uk

ParkNews.co.uk

tollerton.org

westbridgford.co.uk

 

 

This is NET's response to the letter sent to them by the Iremongers Pond Association on 10th January 2012

Dear Mr XXXXXXXX

Thank you for your interesting document, I have forwarded this to Matt Orchard as you have requested. Matt who works for Tramlink Nottingham is best placed to respond to the majority of your questions, however, I have provided information where I can.

• Alternative parking to compensate for that lost on Main Road will be provided within a new car park located on the corner of Main Road and Coronation Avenue. This is shown on drawing 241592/900/DWG/504.

• There is indeed a proposed surface water outfall into Iremonger Pond. This will be subject to the consent of the planning authority and the Environment Agency and measures such as oil interceptors will be put in place to ensure that no contaminated surface water runoff enters the watercourse.

• The Environmental Statement for NET Phase Two can be found on the internet via the following link. Chapter 6 deals with noise including wheel squeal from the tramway and Annex 4 (Code of Construction Practice) outline measures to be taken to control pollution during construction.

http://www.nottinghamcity.gov.uk/netphase2/index.aspx?articleid=9341

With respect to the timeline for construction please find details below:

Iremonger Pond

Initial works affecting Iremonger Pond will commence in late January or early February 2012 to erect temporary fencing and vegetation clearance and last for approximately 2 weeks. Where the tramway crosses Coronation Avenue, water pipes, electricity and telecommunications will be diverted out of the way of the proposed tramway. These diversion should commence in March 2012 and will last approximately 5 months.

Removal of part of the old railway embankment adjacent to Iremonger Pond is due to commence in March 2012 and will take approximately 3 months. This is necessary to maintain the flood area available to enable the construction of the flood wall on Coronation Avenue. The works on the wall will commence in summer 2012, once these works to the embankment are complete and will last approximately 4 months.

The track and road junction where the tramway crosses Coronation Avenue are planned for late summer 2012 and will last for approximately 3 months. It is anticipated that the installation of the track adjacent to Iremonger Pond will be in spring 2013 and again will last approximately 3 months.

Following completion of the above, additional work will be required to install poles to support the overhead electric wire and the signalling equipment. Testing and commissioning of the tramway will commence in late spring/early summer 2014.

If you wish to reply to this email, please do so to the Tram email address tram@nottinghamcity.gov.uk.

Kind regards

NET Project Administrator